BEP authorship and information management for a new terminal in Riyadh
Back to Case Studies
AviationJul 2024

BEP

Saudi Airports Authority (via Tier 1 Contractor)

120,000 m²Terminal area
47EIR requirements traced
100%On-programme information exchanges
0Non-conformances at Stage 4 gate

The Challenge

Author a procurement-ready BEP for a 120,000 m² terminal expansion that satisfied both the Saudi BIM mandate and the client's specific EIRs, then manage information delivery through Stage 4.

The Outcome

BEP accepted at first submission. Information exchanges completed on programme through Stage 4 with no non-conformances raised by the employer's information manager.

/Why They Needed Help

The

Dual-standard compliance

The project had to satisfy both the Saudi national BIM mandate and the client's own employer information requirements — 47 specific requirements that went beyond the mandate's minimum. The contractor lacked the specialist knowledge to author a BEP that addressed both.

First-time BIM adoption for the contractor

The Tier 1 contractor had delivered conventional projects in the region but had not previously managed a project under the Saudi BIM mandate. They needed both the BEP itself and the capability to deliver against it.

CDE governance gap

Information was being shared informally through email and shared drives. A managed CDE with defined submission and approval workflows was needed before any information exchange could be governed.

/Scope of Work

What

01EIR gap analysis and BEP authorship
02CDE setup and information management through Stage 4
03Model submission review and acceptance/rejection against BEP criteria
04ISO 19650 compliance documentation
05Stage gate submission package preparation
/Key Challenges

What

Dual compliance

Contractor capability gap

/Our Strategy

How

01

EIR traceability matrix

Every one of the 47 EIR requirements was mapped to a specific BEP commitment, with the delivery mechanism, responsible party, and evidence format defined. This matrix became the governance tool for the entire project.

02

Capability uplift programme

For the three under-resourced appointment packages, we ran a parallel enablement programme covering CDE submission workflows, model quality checks, and information exchange procedures — practical training tied to project deliverables, not generic BIM training.

03

Gatekeeper CDE management

We operated the CDE as a gatekeeper: every model submission was reviewed against the BEP acceptance criteria before it was shared with the employer. Non-conforming submissions were rejected with written feedback within 24 hours.

/Full Story

The

The Saudi BIM mandate applies to all public infrastructure projects above a defined threshold. For a terminal expansion of this scale, compliance was non-negotiable — but compliance alone was not the brief.

The client's employer information requirements ran to 47 specific requirements across model quality, information exchange, and asset data delivery. Our brief was to author a BEP that traced every EIR requirement to a specific delivery commitment, then manage the information environment through to Stage 4.

The BEP authorship process started with a gap analysis: mapping the contractor's existing BIM capability against the EIR requirements to identify where additional resource or process change was needed.

The information management role through Stage 4 involved running the CDE as the gatekeeper for all model submissions, reviewing each submission against the BEP acceptance criteria before it was shared with the employer.

At Stage 4 gate, every EIR requirement had a documented evidence trail in the CDE, and the information manager sign-off was achieved on first submission.

/Deliverables

What

BIM Execution Plan

A procurement-ready BEP tracing all 47 EIR requirements to specific delivery commitments, with acceptance criteria and evidence formats defined for each.

EIR traceability matrix

A live document mapping every employer requirement to its BEP commitment, updated at each stage gate to reflect delivery status.

CDE setup and administration

Aconex environment configured with submission workflows, approval gates, and role-based access aligned to the BEP and Saudi mandate requirements.

Capability assessment and training

Gap analysis for each appointment package, with targeted training delivered to close identified gaps before Stage 3 submissions commenced.

Stage gate submission packages

Compiled and reviewed submission packages for each stage gate, with evidence against every EIR requirement documented in the CDE.

/Tools Used

Technology

Aconex
Autodesk Revit
Navisworks Manage
Microsoft Excel
“First-submission acceptance on a 47-requirement EIR is not common. The BEP Neutec authored gave our team a delivery framework they could actually follow, not just a compliance document.”

BIM Manager, Tier 1 Contractor

Client Representative

/Certifications

Certifications

Our certified management systems support consistent quality, information management and controlled project delivery across the work we do.

Information Management certification

Information Management

Quality Management certification

Quality Management

Information Security certification

Information Security

Environmental certification

Environmental

PLAN · COORDINATE · DELIVER · OPTIMISE ·PLAN · COORDINATE · DELIVER · OPTIMISE ·PLAN · COORDINATE · DELIVER · OPTIMISE ·PLAN · COORDINATE · DELIVER · OPTIMISE ·PLAN · COORDINATE · DELIVER · OPTIMISE ·PLAN · COORDINATE · DELIVER · OPTIMISE ·

Let's

Whether you need BIM coordination, digital engineering or end-to-end project delivery support, our team is ready to help you deliver projects with greater certainty, fewer surprises and stronger collaboration.

Start Your Project