The Challenge
Produce a survey-accurate as-existing model of a seven-storey Grade II listed office building where the historic fabric was significantly non-orthogonal and existing drawings were unreliable.
The Outcome
Full point cloud survey and LOD 300 as-existing model delivered in six weeks. Design team confirmed the model eliminated all survey-related RFIs through Stage 3.
The
Better Team Collaboration
Architects, engineers, contractors, and owners share a single digital platform, ensuring everyone works from the same real-time data
Cost and Time Savings
Resolving design mistakes digitally on a screen prevents expensive field-generated rework, material waste, and site delays
Early Clash Detection
BIM integrates systems like HVAC, electrical, and plumbing into a single 3D model to catch physical conflicts (such as a pipe clashing with a beam) before construction starts
What
What
Non-orthogonal geometry
Non-orthogonal geometry Occupied building Non-orthogonal geometry Occupied building Non-orthogonal geometry Occupied building
Occupied building
Non-orthogonal geometry Occupied building Non-orthogonal geometry Occupied building Non-orthogonal geometry Occupied building Non-orthogonal geometry Occupied building
How
Align with Business Goals
Ensure the proposed BIM strategy supports the company's broader financial and operational objectives rather than just adopting software for its own sake.
BIM Maturity & Gap Assessment
Evaluate current organizational processes, team skill levels, tech stacks, and information management practices to define a clear roadmap from current to target maturity.
Standards & Compliance (e.g., ISO 19650)
Adopt recognized industry standards for data management, naming conventions, file structures, and Level of Development (LOD) definitions.
The
Retrofit projects on listed buildings present a specific challenge for as-existing surveys: the assumption that walls are plumb, floors are level, and angles are orthogonal does not hold. In a building with 150 years of incremental alteration, the actual geometry can diverge from the architectural drawings by tens of millimetres in ways that have material consequences for services routing and fit-out tolerances.
We were commissioned to provide a point cloud survey and as-existing BIM model for a seven-storey Grade II listed office building ahead of a full internal retrofit. The existing drawings dated from a 1990s refurbishment and had not been updated since.
The survey methodology was agreed with the lead architect before scanning commenced: a tolerance specification of ±5mm across all floors, with LOD 300 modelling of all structural elements and major MEP services, and LOD 200 modelling of existing fit-out to be stripped.
Scanning was conducted across seven floors over three days, with 340 scanner positions to achieve the required registration accuracy. The point cloud was processed and the registration error verified before any modelling commenced.
The as-existing model was delivered six weeks after survey completion. The design team confirmed at their first Stage 3 coordination meeting that the model had eliminated all survey-related queries that had been anticipated based on the existing drawings.
What
BIM Strategy & Roadmap
A long-term vision and phased adoption plan (typically covering 12 to 24 months) tailored to the types of projects your firm bids on
Training & Enablement Plan
A skill-gap analysis and training curriculum for staff across various roles.
BIM Maturity Assessment
A baseline report evaluating current company workflows, tech stacks, and team skills against industry benchmarks like ISO 19650
Technology
“We anticipated a wave of survey RFIs at Stage 3 based on the quality of the existing drawings. The as-existing model eliminated them entirely — the design team worked from it with confidence from day one.”
Associate Director, Lead Architect
Client Representative